Abstract
This project is a dynamometer building named: (dynamometer Nablus ) in Nablus. And its consist ofGround Floor: 584.5 mFirst Floor: 584 mtop Floor: 240mThe contract interval time is 350 calendar days and the contract use in this project unit price contract.And the total cost of the project was 490,000 dollar, and the percent of the profit 5%.
This project is a dynamometer building named: (dynamometer Nablus ) in Nablus. And its consist of Ground Floor: 584.5 m First Floor: 584 m top Floor: 240m The contract interval time is 350 calendar days and the contract use in this project unit price contract. And the total cost of the project was 490,000 dollar, and the percent of the profit 5%.