ANALYSISAND IMPROVEMENT OF NABLUS ELECTRICAL DISTRIBUTION NETWORK BY ADDING A NEW CONNECTION POINT IN SARRA VILLAGE AND TWO TRANSFER SUB-STATIONS TO FEED THE NETWORK

dc.contributor.authorQassab, Mohammad
dc.date.accessioned2022-09-22T10:14:19Z
dc.date.available2022-09-22T10:14:19Z
dc.date.issued2022-01-18
dc.description.abstractLack of electric power sources is one of main problems in Palestine since the population increased dramatically and the required electric power exceeded the permissible limit. In fact, since the Israeli-Electric Company is almost the primary source of electricity, therefore the electric power are limited. The Palestinians suffer from a shortage of electric power due to increasing of electrical power demand, but Israel Electric Corporation does not keeping up with the increasing demand. Nablus also suffers from a shortage of electric power due to the existence of new buildings and the sharp increase of population. In addition, the total electric power supplied to Nablus from connection points has the capacity of 65 MW, but electrical loads reached their peak especially in winter. Consequently, North Electrical Distribution company (NEDCO) cuts off some loads from certain areas in Nablus network for periods of time that exceed an hour per day in order to reduce the pressure on the other connection points in the same electrical network because loads exceed the permissible limit. This leads to failure in electrical transformers as well as in transmission lines and devices. At SARRA connection point, which is one of the connection points of Nablus, the capacity of the substation is 80 MW, and the used capacity is 40 MW. In this study, the researcher aims to examine the analysis and improvement of Nablus electrical distribution network by adding a new connection point in SARRA village and two distribution sub-stations to feed the network. There, a distribution substation was added in two areas with a capacity for 20 MW to each substation, named: Nablus Al-Jadida and An-Najah National Hospital. In fact, the electric power capacity has been raised to 105 MW for the city of Nablus. In this study, the problem was solved considerably by providing new areas with electric power and redistributing the loads from other connection points located in the Nablus city, especially in the eastern industrial area, and new overhead and underground electric transmission lines have been established. The value of the electric capacity supplied from the connection points to the city of Nablus has decreased, and there is a possibility of future expansion and supplying areas in the future due to the presence of electric energy capacity at the new connection points, according to the results found in this study. Also, economic feasibility of the project was prepared and the initial cost value has been calculated.en_US
dc.identifier.urihttps://hdl.handle.net/20.500.11888/17469
dc.language.isoenen_US
dc.publisherجامعة النجاح الوطنيةen_US
dc.subjectelectric loads, the Israeli- Electric company, electricity distribution in Palestineen_US
dc.supervisorDr. Maher Khammashen_US
dc.titleANALYSISAND IMPROVEMENT OF NABLUS ELECTRICAL DISTRIBUTION NETWORK BY ADDING A NEW CONNECTION POINT IN SARRA VILLAGE AND TWO TRANSFER SUB-STATIONS TO FEED THE NETWORKen_US
dc.title.alternativeتحليل وتحسين شبكة التوزيع الكهربائية لمدينة نابلس عن طريقة إضافة نقطة ربط جديدة في قرية صرة ومحطتي تحويل لتغذية الشبكةen_US
dc.typeThesisen_US
Files
Original bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
محمد توفيق نصوح قصاب.pdf
Size:
12.01 MB
Format:
Adobe Portable Document Format
Description:
full text
License bundle
Now showing 1 - 1 of 1
Loading...
Thumbnail Image
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description: